20x30 in NE Wisconsin

Started by Nate R, September 16, 2020, 10:02:23 AM

Previous topic - Next topic

0 Members and 1 Guest are viewing this topic.

pmichelsen

Quote from: Nate R on October 25, 2020, 03:22:52 PM... and not ONE trip to the home center required in that time! :)

Now that's a real accomplishment! I remember some early work trips where it seemed I was making daily trips to the supply house  d*.

Nate R

10/10 and 10/11: With the ladder set overhangs, there were parts of the roof sheathing that didn't have enough support. I knew that, and had bought H-clips, but kept forgetting to put them in when I was sheathing those parts of the roof!  :o   So, I cut 1/4" off some 2x4 chunks so I could wedge them in, and put solid blocking under those seams of sheathing.

I decided to use the "hybrid" detail from JLC of flashing my roof/drip edge/fascia. This protects against ice dams backing up AND bulk water. The downside was that I had to have the fascia in place before the roofing went on.

https://www.jlconline.com/how-to/roofing/drip-edge-and-ice-barrier-membrane_o




For fascia, I had considered my options. PVC and engineered wood were about $28/ea for a 1x8 in my area. PVC was out as I couldn't paint it a dark color. The store we purchased from offers wood boards in "standard," "quality," and "select" grades. The select was also like $26/ea for a 12 ft 1x8. The quality was $12, and the "standard" board was $8.   So, I chose to go with the $12 option. I purchased a couple extras, so we had options. This worked out OK in the end, we ended up with enough straight enough boards for less than an engineered option.

So, all the fascia had to be painted and hung. We got that done on Saturday. I used Pittsburgh Paints' "Paramount" exterior paint, and had a great experience with it! VERY thick, good coverage and flowed well off a brush. MUCH better than the "high" end Behr paint I'd used on my house trim earlier this year.  We'll see how it holds up.

Sunday, we adding the flashing tape to the fascia/roof sheathing joint, and then installed drip edging. Ran into my first time needing something offsite. ....I had nothing to cut the drip edging with. I was able to borrow a snips from a neighbor, thankfully. Saved me a trip into town. Got the drip edging installed, and then started on the ice/water shield. I'd watched a couple videos on how to install it, and thought it'd be a snap. That was NOT the case. I realized later the videos were on a 3:12 or 4:12 roof, and my 6:12 meant I couldn't roll it out without it sliding off, even with a nail or 2 tacked in. So I ended up cutting 16-18 foot chunks instead of the whole roll, and did my best to keep it straight and unwrinkled. It was cold enough on Sunday that it wasn't adhering well, either. We WERE above the manufacturer's minimum install temp (w/o primer), but still wasn't sticking great. Eventually we got it on well enough, and I moved onto the roof underlayment higher up. Finished that up as it was getting dark on Sunday and headed home.

Oh, and forgot to add we met with an electrician on Sunday. Once the power company told me it would be FREE to have power run from the pole on the road to a meter pedestal, we decided it was worth it. I should've looked into it years ago! My local inspector required I have a licensed electrician then rough in my wiring in the cabin once she heard I'd be grid-tied. So I hired one to drop the meter pedestal with an exterior panel, and then trench to the cabin, put a panel in there, and do the rough wiring. We'll pay him about the same as we would've spent on a small setup of off-grid solar panels, wiring, inverter, battery, etc.... So I'd much rather pay the monthly cost, but be able to microwave my lunch, or heat with electric as a backup, etc :)   So I guess we won't be off grid, but now merely a "dry cabin."  Fine with me for that price...I'd always assumed it'd be thousands for the power co to bring in power. I get the impression our local company USED to charge a LOT more for new installs....neighbor nearby went from solar panels for 15+ years to paying to have power run over 1/4 mile a couple years ago.





pmichelsen

Quote from: Nate R on November 01, 2020, 07:42:54 AMIt was cold enough on Sunday that it wasn't adhering well, either. We WERE above the manufacturer's minimum install temp (w/o primer), but still wasn't sticking great.

I'd almost rather have that, it was around 100 out when I did it on my roof and when the Grace got within about a foot of the roof it was stuck (not really but it sure felt like it).

Nate R

10/16-10/18

A big storm come through on Monday, the day after the roof underlayment went on! Fortunately, a relative was in the area Tuesday, and was able to check for me that I hadn't lost the underlayment over the ridge or anything, so things were OK. Some wind damage in other areas, so I was glad to come out OK. :)

I took Friday off work, looked to be better than Monday as far as weather goes. Came up early Friday morning, was about 31 degrees, and a light dusting of snow had fallen overnight. I spent Friday (alone) putting shingles on one side of the roof. Started on the side where the snow had melted off early due to sunlight. I had to be very careful with the cold, stiff shingles. Made sure not to bend/crack them, etc. The weather was NOT as forecast, and ended up getting a bit of rain in the afternoon, that turned to snow, and then a bit more rain. :-p Despite that, I was able to complete one side of the roof on Friday. (about 410 SF of roof).



My wife came up Friday after she got done with work. Cold that night, about 31 degrees where we slept.
Saturday, rain was in the forecast. It was raining when I got up, and about 32 degrees. We worked Saturday morning on a couple remaining pieces of sheathing, and put in an entry door. This door is temporary, and eventually will just be an interior door between our entryway and the rest of the cabin.
By Saturday late afternoon, the rain (and a bit of snow!) had stopped, and things dried a bit. Got a start on shingling the other side. We tried to stay warm, keeping a fire going in the firepit, but was pretty miserable being 30s and wet/damp.



Sunday, I was able to finish the shingles, and put the ridge vent on. Got a rolled ridge vent, what a pain that was to align alone, and get nailed in straight! I wish I had used the ridge vent that comes in 4 foot straight sections, but too late. We hit our 2nd missing material/tool snag....I had no roofing cement! Hadn't even thought about it, but needed it for the ridge vent install. My wife was able to run to town and get some, fortunately. So we got the ridge shingles installed after the vent was on, right as the sun was starting to set.

Phew! Happy to have the roof done! It was a good experience to do it once, but not sure I'll sign up to do it again... But that's why I'm doing this, right? I wanted to build something myself in my life, but not necessarily make a career out of it! :-D




Nate R

Quote from: pmichelsen on November 03, 2020, 07:49:33 PM
I'd almost rather have that, it was around 100 out when I did it on my roof and when the Grace got within about a foot of the roof it was stuck (not really but it sure felt like it).

Hadn't thought about the other extreme.......Yeah, good point, that might be more of a pain if it's WAY warm!

I also felt WAY better when I watched a recent This Old House and saw even the pros weren't getting that stuff down wrinkle-free.  ;D


Don_P

Looks good, I'm sure you're glad to b dried in. There's really 2 good roofing days per year and I'm usually doing something else  ;D.

Ernest T. Bass

Cool project! Covering foam around the foundation has always been a problem area for me as well.. You're probably not too far from where I grew in Silver Cliff WI. Moved to the UP 15 yrs ago.

Our family's homestead adventure blog; sharing the goodness and fun!

pmichelsen

Looking good! As much of a pain as it was to do my roof, it does give me a sense of pride every time we pull up and see that roof.

Nate R

Quote from: pmichelsen on November 21, 2020, 04:58:11 PM
Looking good! As much of a pain as it was to do my roof, it does give me a sense of pride every time we pull up and see that roof.

Thanks! I'm feeling the same now.


Quote from: Ernest T. Bass on November 15, 2020, 09:39:19 PM
Cool project! Covering foam around the foundation has always been a problem area for me as well.. You're probably not too far from where I grew in Silver Cliff WI. Moved to the UP 15 yrs ago.

Yeah, wish there was a better solution. Again, I think I'll be replacing some of this with the pre-coated panels from Styro. In fact, I damaged one of the FRP sections already, so I'll probably order some new foam next year already.  d*



10/24: With the freezing temps and no heat, my wife and I didn't' want to stay overnight again. We came up early Saturday morning. Collected cut shingles, plywood, plastic, and whatever we could fit into her car, and made a run to the landfill/dump, only open in the mornings on certain Saturdays. Got rid of 360 lbs of stuff that way. I've been surprised we haven't had more waste from this process so far.

Then we cleaned some things up inside and out, got things away from the walls so the electrician could work inside.  Also patched in the last small pieces of sheathing. We put up a temporary housewrap for the winter. (Just as an extra layer of protection, and overlapped the foundation insulation so it will stay dry this winter). Cold, we headed home Saturday evening.



NathanS

Looks great. A good roof overhang is so important, not just for protecting the walls/openings from rain, but for aesthetic reasons.

GaryT

That's going to be a cool place, and a real point of pride for you and your wife.  Well done.  And always good to keep a jobsite clean!
Gary

Nate R

The following week, the electrician installed a meter base and outdoor panel, and trenched...ran conduit to the cabin and put a 100A panel inside. Inspector OK'd it and power co has been notified. Nice! We already planned to plant a bush between the cabin and the meter to obstruct that view.... So hopefully we won't see it soon enough.

11/7: Came up again just for the day. Hit the 60s during the week with sun, and the shingles have heated up and most have relaxed at least!  Came up to mostly get ready for deer hunting. Checked on the electrician's work, and then went to the family's land to check on tree stands and such. Power co still has to run the line from the pole to the meter, likely within the next 2-3 weeks. Electrician has run boxes and such inside, but no wires yet.

Windows and front door are ordered, and should be delivered up there around Thanksgiving. Still need a patio door.











Nate R

Quote from: NathanS on December 03, 2020, 01:03:23 PM
Looks great. A good roof overhang is so important, not just for protecting the walls/openings from rain, but for aesthetic reasons.

I agree, it never quite looks "finished" or "right" with no or too small overhangs.  ;D

Quote from: GaryT on December 03, 2020, 01:44:27 PM
That's going to be a cool place, and a real point of pride for you and your wife.  Well done.  And always good to keep a jobsite clean!
Gary

Thanks! And yeah, good to clean up! Wish I could KEEP it clean as I go.  d*

Nate R



11/20 Up for deer hunting, staying in a nearby rented cabin. Spent a few hours at our cabin place though. In the week prior, the Power Co was out, replaced a pole and transformer, ran underground lines to our meter base, and installed our meter. We had power! Got to check out the rest of the electrician's work, he did a nice job on it. Local inspector came by when he was done and approved the cabin work so far, as well as the rough electrical. I was worried about the inspection, as I did a few things that aren't 100% run of the mill conventional, but all was OK!

Got some red pine logs that were sitting for a year+ bucked and split, and confirmed that red pine MUST be under a roof in my woods if it's going to dry, seems it doesn't dry out. Splits were 40+% moisture content inside, starting to think about rotting. Wood shed, or at least temporary wood covering for now, is on the list for next year. My wife and I walked through some things for the interior walls and such, decided that the patio door in the bedroom will be sliding and not swinging for clearance issues. No deer for us this year.



MountainDon

Looks good. Better than your average DIY tossed together cabin
Just because something has been done and has not failed, doesn't mean it is good design.

pmichelsen

It's nice that everything is underground, I worry during every wind storm that my power it going to fall victim to a rouge limb.

Nate R

Thanks, Don!

Yeah, love the underground power, seems to be the standard now for the PoCo. At the road, the lines are above ground, but they've been moving some of those underground in the area as poles come up for replacement.

12/11 I was supposed to have the windows and front door delivered before Thanksgiving. Windows were in, but door manufacturer got delayed....12/23 was the new estimated arrival, a month later than originally quoted. It all worked out, as I then quoted a sliding patio door through that vendor, and they were cheaper than our other option for a black exterior patio door at our local Menards. So I added that to the order. Should have ALL of our windows and doors on site by the end of the year.  So, the vacation day I reserved for delivery was available.

Was a good day to take off work, and open for antlerless hunting. Also wanted to get more oak firewood on hand. During hunting a couple weeks prior, I had selected a tree on the family's 40 acre plot (just down the road) that broke in a 2019 windstorm. A slim red oak. Cut it down, bucked it into carryable logs, and moved some of them to the cabin land. I'm experimenting a bit with how fast I can dry this oak in a few places. Hoping the attic in my full time house will be a mini kiln....by my guesses, I need more dry wood set aside for next year. We'll see if I can get some of this under 20% by a year from now.

Did some hunting after that, no dice. Headed home.











Nate R

1/8/21
The patio door and entry door were at the vendor just before Christmas, and the windows already there too, but they could not deliver it all until after the new year. So took a day off work and met the delivery guy at the cabin. Paid an extra $275 to have them deliver them 170 miles away from their shop. This was WELL worth it, as it was all their responsibility until I had them inside.
We ordered Marvin's Essential (all fiberglass) windows, black inside and outside, as well as the jamb extensions in black. Also a black sliding patio door from Marvin, and a ThermaTru entry door, painted black. Not cheap, but windows and doors are an important design element to us. 
Was able to split some more wood and take delivery of the windows and remaining doors. They look great, and all appeared to be there and correct!  My main windows are a bank of 3 in a 9 foot wide opening by 6 feet tall, so getting those inside was a relief.

The way things are going, I don't forsee a lot of further work here until I finish re-siding my main house this year. So there might not be much to add/see until July-ish? But that was part of the agreement between my wife and I to start this project. I wanted a box up in 2020, and I got that. My goal for 2021 is to get the cabin to the point that it's comfortable (temperature wise) to stay in for next winter. Lots to do in order to get to that point:

Frame interior walls
Air sealing details around the shell
Install skylights  (2 going in )
Install chimney and wood stove
Add soffit vent chutes
Run a bit more wiring
Insulate
Install windows (and final house wrap)
Install patio door, swap outside door with the final one
If I get that much done, I'll start installing the final exterior parts, like window/door trim, siding, soffit, etc.


Window Example



9x6 window bank and wood stove



Eventual front door



Patio Door



Saw this little shrew, even got to pet it!



Got to see how much snow made it onto the porch.....not bad!



Also got to see how well the 2 foot overhangs kept snow off the building.



Hoping to see a chimney and windows from this view later this year....


Don_P

Looking good, windows and doors are a big chunk.

One thing to think about is moving that wood away from the house before the bugs start moving this spring. I've had to do pretty extensive repairs to houses where the bugs moved from the firewood into the wood of the building. I'll stack about a weeks worth at a time on the porch through the winter, the rest of the time its in the woodshed.

Nate R

4/2/21
After nearly 3 months away, I was able to stop by for a few hours. Mostly checking on things, bringing up a few items, and getting some of my things organized for my turkey hunting trip at the end of the month. Everything looked fine, which was a bit of a relief. The weather has let up a bit, so I'm starting back on the siding project on my main/primary house now, so as soon as that's completed, I'll be back at the cabin work. (Hopefully by the end of July? )

I'll probably start a separate thread tracking my costs for this project soon.

Hope everyone has a great Spring!




Nate R

After working on my main houses' exterior most of this year... And then a short break... We are back at the cabin project! :)

Brought the skylights up on a day trip in August.

Came up another day in August and installed 1 window after pulling off the housewrap, making sure sheathing nailing was good, routing out the window opening, and then installing new, permanent housewrap. Was good practice for the other windows.




Nate R

Labor day weekend, my wife and I got to work.  First up was the patio door. The slab has a.. "notch" cut in it along the wall lines between the covered porch and the interior. It's about 1 ½-2" deep in the concrete, down to the rebar level, basically. This was supposed to be a full thermal break, but the concrete guy had a miscommunication, and I wasn't on site for the pour. So by the time we realized he hadn't put anything in to thermally break the porch, it was too late.

This was the after the fact fix: He cut out a v shaped notch with a saw along the wall lengths. Got the blessing that this was the best solution from the local inspector and a Structural Engineer that worked for the state. I cleaned and filled these with spray foam RIGHT as I put down the sill plates.

Cutting out the sill plate for the patio door, I was able to see how it did. Looked great! Filled the cavity! Cut it flush with the slab (as it had expanded beyond it a bit...), and moved on. So a.... "thermal break lite" to help a little with heat loss to the outside through the slab. Could be better, could be worse. If this was a full time place I'd probably have pushed harder to redo the concrete entirely in that section.






Anyway, we got the patio door put in. Marvin Fiberglass (Essential line). About $1600 for the 6 ft door. We moved on, and were able to get 4 more windows put in after cutting sheathing, housewrap install, etc. Not a bad 3 day weekend, but I only took a few pictures. Oops.






Nate R

I came up late the following week for a 11 day work marathon. My wife came up on the weekends. Had a couple family members come up and help for a few days as well. 
First order of business, I swapped out the entry door for the permanent one. We went with an outswing door, to not have to worry about door swing in our small entryway.  We also got another window put in, and took care of routing the openings, sheathing, housewrap, etc.


   






Next was work on the skylights. Our plan WAS to install 2. It ended up being just one. Struggled and struggled to get the shingles to release from each other. But, on that side of the roof, the adhesive strips were holding INSANELY. So often times the shingle would rip, or the one it was attached to would rip instead of being able to release the tab. Of course this was a special order color, and I only had so many on hand. After struggling to get one skylight in, I decided not to try the 2nd one. We'll leave it as it is. It would have been better to do these when the roof went on, but I was up against the weather and time off clock then, too.

I ordered laminated glass instead of tempered for the skylight. That way if a branch hits it, it won't leave an open hole for weeks when I'm not there, but instead hold together like a car windshield. And, being a venting skylight, I can replace that portion if ever necessary, fairly easily.









Nate R

Got a large delivery after that.. All the soffit materials, interior wall framing 2x4s, fiberglass insulation for the ceilings, soffit baffle material, etc.

Went with R38 batts that I'll stack R19 batts on TOP of where there's room..... Was going to do mineral wool, but the lead time more than DOUBLED as soon as I ordered it from 6 weeks to 12+...I didn't trust that would actually be correct. Cancelled that, tried to find R49 FG. No one had THAT in stock either. So moved to R38 batts and then the R19 where they'd fit.

Took hours to move everything around inside the cabin and out to get the new materials in a convenient spot and out of the weather.

Once that was done, and I had help, got the BIG (9 foot wide, 6 foot tall) window assembly installed. Was a relief to finally get that in, and be able to take in the forest view! It all worked out...the overhangs being any longer would start to block the top of the window view...and glad the window isn't any taller or wider. Happy with how that turned out!








The next day, we made a run to the local landfill and got rid of a bunch of building material leftovers.

NathanS

Your cabin looks top notch, Nate. Really nice design choices with window/door/entry placements. And those windows look top notch.

A cabin that size will heat up so quickly, especially with some attention to air sealing.