16 x 32 Northern Missouri Cabin Build

Started by GSPDOG, May 21, 2013, 06:49:17 PM

Previous topic - Next topic

0 Members and 1 Guest are viewing this topic.

GSPDOG

Well finally the framing and plans are finished with another minor changes we break ground Friday.  Starting with the sewage system and foundation which is the biggest change from the last revision.  We have figured out how to get the concrete trucks across the dam assuming I do not get another heavy rain.  We are going to use to old runway metal across the dam that I picked up from a local airport looking to get rid of them.  They have proven to handle the weight distribution.

Copy of the final plan with the new foundation plan.

Thanks for Reading
Jim Brown