Mono slab

Started by Cbean, August 05, 2020, 08:43:03 PM

Previous topic - Next topic

0 Members and 1 Guest are viewing this topic.

Cbean

Has anyone done a mono slab for the 20x30 I'm waiting on for concreet guy to show up. I figure it will be about 16 yards. I'm hope it's under 6000

akwoodchuck

16 yards is just about right on the money for a mono slab that size...that's IF your form is perfect, and the supplier doesn't short you....take it from me and order a couple extra yards. Running out of mud on a pour REALLY sucks lol...
"The lyf so short, the craft so long to lerne."


Nate R

Had a 20x30 poured last year. 12" thick  around the edges (1 foot wide, 1 foot deep there), tapering to 4" thickness in the middle. (all my bearing walls are on the outside of this structure.) I figure more like 12 yards tops for doing it that way?

Site was prepped already. For XPS foam underneath and wrapped up the sides as well, I paid $4k for mine. 

akwoodchuck

If I'm forming a mono, the footers alone will be 288 square inches in cross section, plus the 4" slab on top of that....plus any center bearing pads....
"The lyf so short, the craft so long to lerne."