Plumbing and then electrical?

Started by dablack, December 05, 2012, 11:05:27 AM

Previous topic - Next topic

0 Members and 1 Guest are viewing this topic.

dablack

We are just about dried in.  I thinking we will be there by New Year's.  So, I'm thinking plumbing should go in first since the DWV lines are NOT very flexible.  Right?  Then run the pex for the feeds, then do electical. 

thanks
Austin

MountainDon

Correct. Ductwork, if any, DWV, fuel gas, plumbing water supply electrical
Just because something has been done and has not failed, doesn't mean it is good design.


flyingvan

don't forget speaker wires, phone lines, and HD cables too if there's any chance you'll ever use them
Find what you love and let it kill you.